Design work on the new church is progressing, including architectural, mechanical, electrical and plumbing design so that a complete set of drawings will be able to be submitted to the Diocese for review. Coleman Engineering Co. will be performing soil borings at the site sometime this fall to verify soil types and conditions. Discussions with Cloverland Electric are underway so that the large utility pole in the middle of the church property can be relocated. Site plan drawings will soon be submitted to Bay Mills Township for an initial site plan review.